What is required for the site plan?

A site plan requires:

  • The entire lot or parcel with dimensions and orient the drawing to the North Arrow
  • Adjacent roads and their names
  • Locations and outside dimensions of all buildings
  • Building setback distances
  • Setbacks for the well and septic systems
  • Significant features or improvement of the subject property, such as:
    • Corrals
    • Fences
    • Irrigation ditches
    • Overhead power lines
    • Ponds
    • Septic systems
    • Streams
    • Towers
    • Wells
  • Driveway location

Show All Answers

1. Should I contact anyone before beginning a project?
2. What is a zoning certificate?
3. When do I need a zoning certificate?
4. Where can I find a Zoning Certificate Application?
5. When does the zoning certificate expire?
6. What is required for a zoning certificate?
7. What can be used for proof of ownership?
8. Where can I get a copy of my deed?
9. What is required for the site plan?
10. When will my zoning certificate be approved?
11. When will I receive the approved zoning certificate?
12. Can I build my shop (accessory building) first?
13. What if I build without a permit?
14. Why do you need the estimated cost of my new structure?
15. Do I have to get a wastewater (septic) permit before a zoning certificate?
16. When can I begin construction?